Design-Build Project Capabilities
APS chose proven and resilient technologies to successfully achieve the objectives of the Redhawk Power Station wastewater treatment facility. The Zero Liquid Discharge (ZLD) System had to reclaim water resources and reject waste properly as an integrated component of the power station.
To accomplish this, the HPD-designed process utilized brine evaporation and crystallization systems, which were the key elements in the overall design. The evaporator was designed to receive 450 gpm of high salinity blowdown from the cooling towers. The compressor-driven evaporator pre-concentrates the brine and produces high purity distillate for recycling to the cooling tower and service water system.
Concentrate from the evaporator is advanced to the crystallizer where the salts that form the impurities are crystallized and sent to a centrifuge for dewatering. The crystallizer is also compressor-driven and produces distillate that is combined with that of the evaporator for recycle.